Short answer

The cost of unplanned downtime is (lost margin per hour + idle labor + overtime + scrap + penalties) × hours of downtime. MTTR is total repair time divided by the number of breakdowns. To see where your time goes, split each breakdown into four phases (notification, diagnosis, repair and verification) and measure each one for a month in your own plant.

Many plants know their OEE but not what an hour of stopped line really costs them, or which repair phase eats the time. Without those two figures it is hard to justify an investment in preventive maintenance or better diagnostic tools. This guide explains how to calculate both with the data you already have.

1. How to calculate the cost of one hour of downtime

Add these five items to every hour of downtime. Some apply in any plant; others depend on your customer contracts and on how you recover lost production.

Item What it includes Where to get the data
Lost marginGross margin on what is not produced per hourManagement control: units per hour × unit margin
Idle laborOperators who cannot produce while the line is downNumber of operators × hourly payroll cost
OvertimePremiums paid to recover production or repair outside shiftsHR and maintenance work orders
ScrapRaw material and work in progress lost when the line stopsProduction and quality
PenaltiesLate deliveries that carry contractual penaltiesCustomer contracts and logistics

Illustrative example with assumed figures

Imagine a line with €1,200/h of margin, 6 operators at €28/h (€168/h), €90/h of overtime and €150/h of scrap, with no penalties. Cost per hour: 1,200 + 168 + 90 + 150 = €1,608/h. If the breakdown lasts 2.5 hours, the stoppage costs €4,020. These figures do not come from any study: replace them with your own plant's numbers.

2. How to break MTTR down into four phases

An average MTTR hides where the time is lost. To see it, record four timestamps on every work order:

  1. Notification and arrival: from the moment the machine stops until the technician is at the line.
  2. Diagnosis: from arrival until the technician knows what is failing. This includes finding the schematic, interpreting the alarm code and locating the spare part reference.
  3. Repair: the physical intervention.
  4. Verification and restart: tests and return to production.

After a month of data you will see which phase weighs most in your breakdowns. If diagnosis accounts for a large share, the problem is access to information, not technician skill.

3. What to do if diagnosis is your bottleneck

A search tool over your manuals, such as IgeraIndustria, can shorten diagnosis. Measure the effect in your plant by comparing diagnosis time before and after, rather than relying on generic figures.

Calculate with your own data

Use the OEE calculator to see how much capacity you lose and the preventive maintenance plan generator to start reducing breakdowns. If you want to see how a manual is queried in seconds, take a look at IgeraIndustria.

Frequently asked questions

What should I include when calculating the cost of an hour of downtime?

The margin you stop earning, idle labor, overtime to catch up, scrap and contractual penalties. If you lack any of these figures, start with lost margin and idle labor and fill in the rest over time.

How is MTTR calculated?

Add up the repair time of all breakdowns in a period and divide it by the number of breakdowns. To make it useful, calculate it per machine or machine family, not just for the whole plant.

Why measure diagnosis separately from repair?

Because they need different fixes. A slow repair improves with training, tools or spare parts; a slow diagnosis improves with better documentation, breakdown history and identified spare part references.

How much will a manual search tool reduce MTTR?

It depends on your plant, the quality of your documentation and how much time you lose on diagnosis today. That is why it pays to measure MTTR by phase before rolling it out and compare afterwards.

⚡IgeraEnergy & ConstructionSolar CAEs & Construction Kit
GUÍA TÉCNICA (TXT)

2026 Energy Savings Certificates (CAEs), Collective Solar & Construction Subcontractor Compliance Kit

90-second solar lead qualification script + Energy Savings Certificates (CAEs) & subcontractor compliance checklist.

  • Automated WhatsApp solar lead qualification (utility bill OCR, roof type, local tax incentives)
  • Collective self-consumption quorum rules and dynamic sharing coefficients under RD 244/2019
  • Monthly construction subcontractor compliance checklist (REA, social security, liability insurance, H&S)
Portfolio / company size (optional, 1 click):

Instant download · No card required · 100% spam-free

Share this article

Help spread knowledge by sharing this content with your network